Case Study

Mellors Lodge, Nottingham

Sector
Supported Living
Location
Nottingham
occupancy
36 Flats
Service
Plant Room Refurbishment

The Challenge

The existing plant room at Mellors Lodge was approaching the end of its serviceable life, operating at reduced efficiency and causing downtime to heating and hot water services. The plant served all 36 flats and communal areas, so maintaining heating and hot water throughout the winter period was critical. The key challenge was completing the replacement works while keeping disruption to residents to a minimum.

Our Solution

Prestige delivered a full plant room replacement while working as Principal Contractor under CDM Regulations. Temporary boilers were installed to maintain heating and hot water services during the works, allowing the existing plant to be safely isolated, removed and replaced.

To reduce disruption on site, the majority of the pipework was prefabricated off site at our facility. This helped improve installation efficiency, reduce time spent working within the live environment and support a smoother changeover to the new plant.

The upgrade included the installation of new Ideal Evomax 2 boilers providing a total output of 300kW, complete with plate separation, a new specialist flue system, two new 600-litre unvented cylinders, new plant components, electrical works and BMS integration. An Elexion chemical-free water treatment solution was also installed to support system protection, water quality and long-term performance without traditional chemical dosing.

The Result

The new system was fully commissioned and handed over to the Prestige maintenance team for ongoing planned and reactive support. The completed works provide Mellors Lodge with a modern, reliable and maintainable heating and hot water plant serving residents and communal areas.

“I would like to take this opportunity to provide positive feedback regarding the recent boiler system replacement project.

This was a significant and complex piece of work involving the removal and replacement of boilers and fire pellet units, as well as the installation and operation of a temporary boiler system over a number of months to ensure continuity of service. Given the scale and complexity of the project, the service delivered throughout was excellent.

Whilst there were a small number of technical issues encountered during the works, these were addressed promptly and effectively, with solutions implemented as soon as possible. As a result, disruption to customers and day-to-day operations was kept to an absolute minimum.

There were some complaints from customers regarding noise levels during the project. However, these issues were related to the operation of the temporary system and the nature of the works themselves, rather than the conduct or performance of the contractors on site.

In particular, I would like to recognise Bobby for his outstanding contribution throughout the project. Bobby was consistently present on site, approachable, and willing to assist whenever needed. He maintained excellent communication with staff and customers, ensuring that we were kept fully informed at every stage of the works. His professionalism, responsiveness, and commitment to customer service played a significant role in the smooth delivery of the project.

Overall, the project was managed and delivered to a very high standard, and I would like to thank everyone involved for their hard work, dedication, and professionalism throughout.”

J
Jerome Dickson
Services Manager, Places for People

Services Delivered

Plant Room Replacement Temporary Boiler Provision Off-Site Pipework Prefabrication Mechanical Installation Electrical Works BMS Integration Flue Installation Elexion Chemical-Free Water Treatment Commissioning Ongoing Maintenance