The Challenge
The existing energy centre at Stanhope Street, a busy residential area in Newcastle, had reached the end of its serviceable life. The ageing biomass boiler had deteriorated significantly, placing increased demand on the gas backup boilers and reducing overall system efficiency and reliability.
As the plant served 6 blocks, comprising 331 units, all supplied via Heat Interface Units (HIUs) within each property, maintaining heating and hot water throughout the 15‑week programme was essential. The key challenge was delivering a full plant room transformation while keeping disruption to residents to an absolute minimum.
Our Solution
Prestige delivered a complete energy centre refurbishment while acting as Principal Contractor under CDM Regulations, managing and coordinating 11 specialist contractors throughout the works.
The existing biomass boiler, gas boilers, associated pipework and redundant equipment were fully removed. The upgrade included new high‑efficiency Hamworthy modular boilers (2000kW), a plate heat exchanger to optimise system separation, a redesigned flue system, upgraded gas infrastructure, new BMS controls and a full electrical refurbishment. A chemical‑free Elexion water treatment solution was also installed to support long‑term system health and performance.
To minimise disruption, large sections of pipework were prefabricated off site at Prestige’s fabrication facility. This reduced installation time, limited hot works and supported a smoother changeover to the new plant. Building improvements were also completed to enhance access and maintainability for future operations.
The Result
Heating and hot water services were maintained throughout the programme with no resident complaints, highlighting the effectiveness of the team’s planning, communication, and delivery. The new system was fully commissioned and handed over to the client, providing a modern, efficient and maintainable heating and hot water plant that supports long‑term performance for residents across the development.